Duke Energy Underground Line Relocation

Duke Energy will be repairing an existing 138,000-volt (138-kV) transmission line buried under Madison Road in Oakley (Hamilton County). The trench or tunnel that houses the underground transmission line was installed in the 1940s. Previous efforts were unsuccessful for repairing the transmission line in place.

As a result, we will relocate a 0.3-mile (1,700 feet) section of the new transmission line in another area under Madison Road (from Gilmore to Drake) to make the repairs. These repairs are scheduled to start October 9 and continue through July of 2024, will work being done 9:00 AM - 4:00 PM , Monday - Friday.

Duke project site: Oakley Underground Line Relocation (duke-energy.com)


Schedule/Updates

08.06.2024 Updates

  • Crews are presently working just past the car wash and expect to have that portion of the duct bank installed by the weekend.
  • Aug. 7-9: Crews will be doing testing on the duct system that was installed. Expect to see crews working around both manholes.
  • Aug. 26-Sept. 19: Crews will begin pulling the transmission equipment between the two manholes. There will be large equipment and flaggers at either end of the manholes during the first week. We expect single lane restrictions during the first week of Aug. 26. After the first week of Aug. 26, we don’t expect to have as much public impact regarding the construction, perhaps a van and a work truck near the Oak Tavern.
  • Expect minimal parking restrictions the first week, and crews will not be blocking any driveways or parking lots. Curb repairs are underway.
  • We will better be able to determine full restoration/repaving after the testing this week.

03.05.2024 Updates

Beginning Thursday, March 7: Crews will begin cutting into the pavement at the manhole on the opposite end of Madison from the library – near the Clepper-Kelsch Funeral Home building at 2961 Madison. The construction will be crossing the street and then working in front of businesses up to Subway including the Subway restaurant, Oakley Square Animal Hospital, Rooted Juicery & Kitchen, Define Oakley and Dewey’s Pizza. We expect this work to continue through March 13.

01.05.2024 UPDATES


Weeks of January 8 and January 15:

Crews continue working around Skyline Chili. Businesses will remain open, and flaggers will direct traffic. Crews will not work Monday, January 15th

Saturday Schedule:

Beginning January 13 and weather permitting, crews expect to work Saturdays with lane restrictions between the hours of 7 a.m. to 5 p.m. to stay on schedule, as we are still aiming for completion in July.


Week of January 22:

Crews expect to install the next 60-to-100 foot section of trench under Madison Road in front of Bona Decorative Hardware.

10.05.2023

Construction is expected to begin on October 9. The work will begin near the Oakley Library and continue down Madison towards the Square.

07.30.2023

Project Update

Construction for this project is now planned to start this fall. Expect to see planning activities in early July at the laydown yard, located at Duke Energy’s Red Bank Substation off Brotherton Court in Cincinnati. We expect this important component of the electric system to be back in service by May 2024 and will continue to provide updates throughout the project.

05.23.2023

Start of this project is delayed, as Duke works to get all the appropriate approvals. Watch for updates & revised schedule when we get them.

03.02.2023

Duke will be dropping  the postcard shown below on 03/02/2023, informing impacted businesses/properties of the manhole testing work that will be happening the week of March 20th.   There will be flaggers and lane restrictions during the hours of 9 a.m. – 4 p.m. 


03.07.2023

OCC First Tuesday Meeting - Duke representatives will present project details.


Become a Member. Join Oakley Community Council and get involved in helping us implement the vision laid out in our Oakley Master Plan. -- Join Us


"Oakley Community Council" is a 501(c)3 non-profit organization. Cincinnati, OH 45209 -- Bylaws
Powered by Wild Apricot Membership Software